Drywall & Framing subcontractors
Drywall & Framing subcontractor COI requirements
Drywall and framing subs are labor-heavy, thin-margin firms that grow by adding sub-tier crews. Their COI defect rate sits right at the industry average, but the defects are distinctive: classification limitations that cover only interior drywall, residential exclusions on mixed-use projects, sub-tier crews without workers compensation, and CG 22 94 removing coverage for the work those crews perform.
Drywall & Framing audit
Northgate Drywall & Framing LLC
Pier 9 Residential Tower
- CGL policy
- GL 1907-6634-28
- AM Best
- A- VII
- Carrier
- Prairie States Indemnity Co.
- DeficientWC
Two declared sub-tier crews have no workers compensation on file.
- DeficientCG 22 94
Subcontracted work exclusion attached to the CGL.
- DeficientResidential
Condominium exclusion on a project with 212 residential units.
- of drywall subcontractor COI packets are deficient on first review
- 71%
- of drywall subcontractor COI packets are deficient on first review
- Pikorua Security 2026 Benchmark
- trade rank by defect rate, 0 points above the all-trade average
- 7 of 14
- trade rank by defect rate, 0 points above the all-trade average
- Pikorua Security 2026 Benchmark
- of subcontractor and vendor COIs contain material coverage deficiencies or missing endorsements on first review
- 71%
- of subcontractor and vendor COIs contain material coverage deficiencies or missing endorsements on first review
- AGC Risk Committee Audit
- of COIs claiming additional insured status fail to attach the CG 20 37 completed operations endorsement
- 64%
- of COIs claiming additional insured status fail to attach the CG 20 37 completed operations endorsement
- IRMI Construction Risk Survey
Typical exhibit
Typical drywall insurance requirements
- Rules in template
- 14
- Hazard tier
- Significant
| Coverage | Typical limit | What to check |
|---|---|---|
| Commercial general liability (CG 00 01, occurrence) | $1,000,000 each occurrence / $2,000,000 general aggregate | Classification on the policy must match the scope: metal stud framing, drywall, acoustical ceilings and exterior sheathing are often rated separately. |
| Products-completed operations aggregate | $2,000,000 | Water intrusion through exterior sheathing and fire-rated assembly defects are the long-tail claims. |
| Business auto liability | $1,000,000 combined single limit | Crew trucks and material deliveries; hired and non-owned autos when crews drive personal vehicles. |
| Umbrella / excess liability | $5,000,000 each occurrence and aggregate | Scaffold and lift falls are the severity driver for this trade. |
| Workers compensation / employer's liability | Statutory / $1,000,000 each accident, $1,000,000 disease each employee, $1,000,000 disease policy limit | The defining issue for this trade. Request WC for every sub-tier crew; uninsured sub-tier payroll is often charged back to the GC's own WC at audit. |
Endorsement checklist
Forms to see attached, not just checked
- CG 20 10Additional insured, ongoing operations
- CG 20 37Additional insured, completed operations
- CG 20 01Primary and noncontributory
- CG 24 04Waiver of subrogation on general liability
- WC 00 03 13Waiver of subrogation on workers compensation
- CA 20 48Designated insured for covered autos liability
- CG 25 03General aggregate applies per project
Exclusion watchlist
Exclusions that void drywall coverage
- Red flag
CG 22 94 Exclusion, Damage to Work Performed by Subcontractors on Your Behalf
Drywall and framing contractors rely heavily on sub-tier crews. CG 22 94 deletes the subcontractor exception, so damage to the completed work caused by a sub-tier crew is no longer covered.
Read the CG 22 94 guide - Red flag
Classification limitation exclusion
Carrier forms that limit coverage to the operations described on the declarations, such as interior drywall only. If the sub also frames exterior walls or installs sheathing, those operations are uninsured.
- Red flag
Residential, condominium or tract housing exclusion
Common on interior trade policies. On podium mixed-use buildings with residential floors above, the residential portion of the scope can be excluded.
- Red flag
CG 21 86 Exclusion, Exterior Insulation and Finish Systems
Framing subs that install exterior sheathing or EIFS substrate can trigger this exclusion, which removes coverage for water damage claims behind the cladding.
Sub-tier crews and workers compensation
Drywall and framing work is labor. Contractors expand capacity by bringing in sub-tier crews, often small firms or individual installers paid by the board or by the square foot. Those crews are where workers compensation disappears. If a sub-tier crew has no WC, an injured installer can look upward to the drywall sub and then to the GC, and the GC's own workers compensation carrier may charge premium for the uninsured payroll at audit.
Pikorua Security treats sub-tier crews as vendors in their own right. The drywall sub declares its sub-tiers in the broker upload link, each sub-tier receives its own request for WC and GL evidence, and the parent sub's payment application stays on hold until every declared crew is compliant.
Classification and residential limits
Interior trade policies are priced by classification. A policy rated for interior drywall installation may carry a classification limitation endorsement that excludes anything not described, such as exterior framing, sheathing, fireproofing or acoustical ceilings. A residential exclusion may also remove condominium or apartment floors on a mixed-use podium building.
These limits never appear on an ACORD 25. The only way to see them is the declarations page and schedule of forms, which Pikorua Security extracts on every packet and compares against the scope you assign to the sub in the rule template.
- Compare the classification description on the declarations to the subcontract scope.
- Check for residential exclusions whenever any floor of the project has dwelling units.
- Look for CG 21 86 if the scope includes exterior sheathing or EIFS substrate.
Fire-rated assemblies and completed operations
Drywall contractors build the fire-rated walls, shafts and corridors that protect occupants. Defects in rated assemblies, penetrations and joints can surface during an inspection or, worse, during a fire. Completed operations additional insured status (CG 20 37) and a products-completed operations aggregate that is not shared with dozens of other projects (CG 25 03) are the protections that matter when that claim arrives.
How to verify a drywall sub's COI
A manual review of one COI and its endorsement packet takes 25 to 40 min (CFMA Time Study). These are the six checks, in the order Pikorua Security runs them.
- 1
Match the named insured to the subcontract
Compare the named insured on the ACORD 25 with the legal entity that signed the drywall subcontract, including the LLC or Inc. suffix. A trade name or DBA is not the contracting entity, and additional insured coverage follows the policy's named insured.
- 2
Check limits against your drywall exhibit
Confirm commercial general liability of $1,000,000 each occurrence / $2,000,000 general aggregate, an umbrella of $5,000,000 that follows form over CGL, auto and employer's liability, and statutory workers compensation.
- 3
Read the endorsement pages, not the checkboxes
A Y in the ADDL INSD or SUBR WVD column is not an endorsement. Confirm CG 20 10, CG 20 37, CG 20 01, CG 24 04, WC 00 03 13, CA 20 48 and CG 25 03 are attached as forms, and that the ongoing and completed operations forms share the same edition date.
- 4
Scan the schedule of forms for drywall exclusions
Look for CG 22 94 Exclusion, Damage to Work Performed by Subcontractors on Your Behalf, classification limitation exclusion, residential, condominium or tract housing exclusion and CG 21 86 Exclusion, Exterior Insulation and Finish Systems. None of these appear on the certificate; they sit in the declarations schedule of forms and the endorsement pages.
- 5
Check carrier ratings and policy dates
Confirm each carrier is rated A- VII or better by AM Best and that no policy expires before the drywall scope and its completed operations period are finished. Set renewal reminders at 60, 30, 15 and 0 days.
- 6
Hold payment and site access until resolved
Keep the drywall sub's pay applications and jobsite badges on hold until every finding is resolved, then file the verified packet so it is ready if you ever need to tender a claim.
Try it
Is this drywall COI compliant?
What the packet from Northgate Drywall & Framing LLC shows
Matching editions
OKDeclared in the broker upload
GapOn the sub's CGL. Red flag if present.
GapFraming, drywall, sheathing
OKCondo or apartment floors. Red flag if present.
OKBoth GL and WC
OK
Switch on = present in the packet. Switch off = missing.
Deficient: 2 findings
WC on file for every sub-tier crew
Uninsured crews push injury and audit cost to the GC.
CG 22 94 subcontracted work exclusion
Damage caused by sub-tier work is excluded.
Pikorua Security would send a deficiency notice to the sub and its broker citing each item, and hold payment until a corrected endorsement arrives.
Questions
Drywall & Framing COI questions
Why are drywall subcontractor COIs often deficient?
Can a GC be charged for a drywall sub's uninsured crews?
What is a classification limitation exclusion?
14-day free production trial
Check every drywall sub's endorsements before they mobilize.
Upload your current drywall certificates. Pikorua Security reads the endorsement pages, applies the drywall template and shows every hidden gap in 10 minutes.